A QUARTERLY INDUSTRY PUBLICATION
JobScope
FOR KEY FIELD AND OFFICE PEOPLE IN MECHANICAL CONTRACTING
-about Job Scope -subscribe -archives -links -contact information -home
Winter 2006
key field and office people in mechanical contracting
Job Scope
Job scope story Blue Chip Casino

Major Re-design Helps Float America's Largest Casino Boat
By Don Doherty

Boyd Gaming of Las Vegas wanted to build the country’s largest casino boat operating
on inland waters. The first hazard the ship encountered — albeit long before its hull entered the water — appeared when estimators actually put their calculator to work
on the plan. About $200 million should do it, it was estimated, a cost nearly twice as
high as initially thought. Before the project could get off the ground everyone needed to find a way to cut the price tag nearly in half. Clearly they wouldn’t get there by buying less furniture and cheaper wallpaper. In the end, one of the ship’s initial five decks had to go.
Maus, IPS’s vice president of sales, worked with the marine architect, Guido-Perla Associates, and shipbuilder, Jamestown Metal Marine Sales, Inc., to downsize the mechanical systems for the smaller boat. He was joined by IPS’s president, Robert Lempa, and estimator, Brian Lecea. Helping the IPS team was KJWW Engineering,
a mechanical engineering firm in Naperville, Ill. “We fine tuned everything related to HVAC on the vessel,” Maus said. When a commitment for the new

Above: The casino boat's high end HVAC equipment will normally operate using 100 percent outside air.
Below: Boilers and other heavy components had to be set in the hold deck before erection of the top deck.

Job scope story blue chip casinodesign came from the owner,IPS assigned a project manager,Dave Sawtell, to the job. Much of the project’s design phase overlapped the construction phase. In other words, IPS was building one part of the ship before other parts were even on the drawing board. This was another unusual characteristic of the project. Sawtell said while the ship’s main deck was getting built, drawings for what would be above weren’t yet seen. “We never really knew the whole scope of the job until 6 or 7 months later,” he said.

 

All the drawings and submittals were done onsite, Maus said. “All our submittals and drawings were done electronically. We would have to submit information to the marine architect; they would then approve it.” When it opened to the public on Jan. 30, the new Blue Chip Casino boat in Michigan City, Ind., still claimed the title of "America’s largest floating casino." Two key characteristics of the ship could raise the bar for competitors. One is a far roomier, more stylish casino deck than is typically seen on gambling boats; the other is its heavy-duty, state-of-the-art HVAC system, which operates with 100 percent outside air capable of 15 air changes each hour. Maus said the HVAC system is on a par with a hospital operating room for air quality. “Smoking seems to go hand in hand with gambling,” he said, noting that air quality has been the number-one complaint of patrons of gambling vessels. The owner was careful to make sure it wouldn’t be a problem in the new boat.

 

IPS was the lead mechanical contractor on the job, having contracts not only for HVAC and process piping but also sheet metal, fire protection, and insulation. Being able to coordinate the trades gave the contractor a big advantage; however, it didn’t enable them to decide when it was time to get to work. Installation of mechanical systems had to follow construction of the ship’s hull. The vessel was built entirely in place in a man-made slip alongside a waterway connected to nearby Lake Michigan. The pit remained dry while boilermakers welded sections of steel plate to form the ship’s hull. Chicago Bridge & Iron Co (CB&I), constructed the ship. As the vessel took shape, IPS went to work as completed areas in the lower hold deck became available. There were boilers, chillers, compressors, pumps, air handlers and their related piping and ducts; also process piping for water intakes, bilge removal, ballast tanks — the normal marine systems found aboard ships — and generators the size of automobiles that could supply 100 percent of the ship’s power if it should go to sea: Much, if not all of it, had to be in place before the deck was covered. Mechanical equipment, ballast tanks, and other large components were laid out symmetrically on both sides of the ship’s centerline, or keel, to balance the vessel. Sawtell said the piping, because it was high up, went in first. Behind this came the plumbing, fire protection and ductwork. Crews began in the aft end of the vessel and worked from one side to the other. “As we finished here, another trade moved in. It worked out well,” he said. When the insulators finished, the interior joiners put up the walls and ceilings.

 

Keeping in step with the ship builders required getting materials delivered on time and in the right sequence. Sawtell and Maus worried about delivery of big-ticket items like boilers and chillers, but they said it worked out well in the end. On the flip side of the coin, there was plenty of space onsite to store things that arrived weeks before needed. Piping assemblies were prefabricated as much as possible with all the 8-inch and smaller pipe fabbed onsite.

page 1 - 2

Copyright 2007. Chicago-Area Piping Council, 221 N. LaSalle Street, Suite 3400, Chicago, IL 60601.
All rights reserved. The contents of the publication or this Web site may not be reproduced in whole
or in part, in any manner whatsoever, without consent of the copyright owner.